Project List >24” pipeline in kharg island

 

Project title: 24” pipeline in kharg island

Location: kharg island, Persian Gulf

Client: Iranian offshore Oil company

Jab summary:

Fabrication and Installation of 2000 m of carbon steel 24” pipeline onshore Kharg island.

Main Job steps include:

§  Design and installation engineering

§   Right of way execution

§   Sand blast &anti- corrosion coating of all pipe joints

§    Cold bending of pipe joints at site ( up to 15 )

§    Installation of insulation joints at two tie-in points

§    Pipeline crossing with roads

§    Cathodic protection of pipeline

§     Pipeline hydro test / pre commissioning

 

major equipments involved

§          D9  side booms

§          Earthwork machinery

§          Bending machines

§          Diesel generator and welding machines